Beskrivning
Ellevio plans to install new RTU (Remote terminal units) in appproximately 300 distribution stations in mid-sweden. The frame agreement is planned for 4+2+2 years. Existing RTUs are largely 25 years old or older and will be electrically connected to the station but will also be prepared for digital connectivity.The procurement includes the delivery of hardware, software, technical documentation, support, training, etc.
Öppna originalannonsen hos TED
Liknande
-
Frame agreement RTU for Distribution stations
Ellevio AB · 2025-05-16 · sista anbudsdag 2025-06-13 · 40 000 000 SEK · Upphandling
Ellevio plans to install new RTU (Remote terminal units) in appproximately 300 distribution stations in mid-sweden. The frame agreement is planned for 4+2+2 years. Existing RTUs are largely 25 years old or older and will be electrically connected to the station but will also be prepared for digital …
-
Frame Agreement Power Transformers 6,3-25 MVA
Ellevio AB · 2024-04-11 · sista anbudsdag 2024-05-12 · Upphandling
Frame agreement for Power transformers type: 6,3-25 MVA., HV side 30-50 kV, LV 10-20kV. Contract duration is 4 years with possibility to extend the Contract up to 2 years (1+1). Volume commitment is 6 units per year. The estimated need during the Contract is between 12-18 units per year. The uni…
-
Frame Agreement Power Transformers 6,3-25 MVA
Ellevio AB · 2025-03-21 · 1 SEK · Tilldelning
Frame agreement for Power transformers type: 6,3-25 MVA., HV side 30-50 kV, LV 10-20kV. Contract duration is 4 years with possibility to extend the Contract up to 2 years (1+1). Volume commitment is 6 units per year. The estimated need during the Contract is between 12-18 units per year. The uni…
-
Utbyte av stationsautomation och reläskydd i fördelningsstation F1 Kantorn
Gävle Energi AB · 2024-05-08 · sista anbudsdag 2024-06-10 · 8 900 000 SEK · Upphandling
Gävle Energi AB har för avsikt att under 2024-2025, investera i ny stationsautomation och reläskydd för en befintlig 77/11kV fördelningsstation, F1 Kantorn.
-
Utbyte av stationsautomation och reläskydd i fördelningsstation F1 Kantorn
Gävle Energi AB · 2024-12-02 · 6 287 374 SEK · Tilldelning
Gävle Energi AB har för avsikt att under 2024-2025, investera i ny stationsautomation och reläskydd för en befintlig 77/11kV fördelningsstation, F1 Kantorn.